Temporary Traffic Lights  

We can provide 2, 3 or 4 way temporary traffic light setups; inclusive of a pedestrian crossing, if required. WSW will handle every stage of the process for you. This will begin with the production of any required TM plans, followed by the application for a highway licence with the relevant authority. Upon approval, we will set out all signage and temporary signals to Chapter 8 standards, on the day you have chosen for the works to begin.

 

 

Please note, to obtain a highway licence, the following minimum notice periods to the local authority apply:

traffic-signals.png

Traffic control / road category

Minimum notice period

Stop/go boards*

 

Two way signals*

 

Multi phase signals

 

*All signals on primary/district routes

14 days

 

14 days

 

21 days

 

21 days

Road Closures

For some works, a full road closure is the most appropriate solution. Again, we will handle this entire process for you, ensuring a professional TM plan is produced that showcases how traffic will be diverted most efficiently. On the day the work is scheduled to begin, all relevant signage will be in the correct location, ready for you to get started.

 

 

Please note, to obtain permission for a road closure, 30 working days (6 weeks) notice is required by the local authority.

PR555-A4L-V-xl (1).png
Foxdale Road Closure
Road Closure in Douglas

And more.

From parking suspensions, to lane closures, or even individual professional CAD TM drawings. Get in touch and we will do our very best to accommodate your needs.

 

 